The $8,000 HVAC Mistake That Never Happened
The Problem
Original plans showed air conditioning units conflicting with ceiling lighting layout. The HVAC contractor planned to install units directly where recessed lights were specified.
Our Solution
During plan review, we identified the conflict and redesigned the ceiling layout to accommodate both systems efficiently.
Timeline
Caught in design phase - 2 weeks before construction
Outcome
Client avoided demolition, rework, and delays. Project completed on time with properly integrated systems.